  • Phase one and two of the landscaping surrounding the expressway were completed in December 2010.
    In April 2010, ground was broken for the island’s main sewage plant. This is scheduled for completion by the third quarter of 2012.
  • Deep services including Sewers and storm water pipes for the museum district have been installed and are due for completion in the second quarter of 2011. 
  • All four of the 132kV electrical substations are complete with one becoming fully operational in January, and the second one due for full operation in the third quarter of 2011.
  • TDIC has recently awarded the contract for the district cooling plant operation on Saadiyat to a joint venture partnership between Dalkia and Arcapita. The 29 year concession will incorporate three plants, and will be one of the Middle East’s largest district cooling plant operations, providing services over a 27km2 area.